Phase 1 – Work commenced August 2014 working on the 8th floor – CEO office area. Carrying out mains infrastructure, lighting and feature lighting, small power, fire alarm.
Project Value: £270,000
Phase 2 & 3 – Work commenced October 2014 working on Levels 4 to 7 as above
Project Value: £1.6 million
Phase 4 – Ground Floor West – Relocation of existing tenant to enable formation of new structural staff entrance
Project Value: £100,000
Phase 5 & 6 – Ground Floor East, 1st & 2nd Floors currently on going.
Electrical enabling works for the new structural staff entrance. Works to be complete end of June 2015
Project Value approx: £100,000